Equipping of Well No. 59

1607 S. Ninth St.
July 2017 - April 2019
This project consists of constructing a new municipal water well pump house building for the equipping of Well No.59 that includes well pump and motor, discharge piping and valves, chemical feed system, electrical switchgear and instrumentation, new fence wall and gates, and other site improvements.  This project will replace an existing well which has reached the end of its useful life, and will improve the reliability of the water system.

Project Locations

​To see project details click the enlarge icon " [ ] " on the map below:

Project Features


  • Equipping of Well 59 with pump house and other site improvements
  • Water System Improvements​

Project Team

Project Manager: Tim Flint
(714) 765-5271

Contractor: Arnaz Engineering Contractors
(714) 666-1765


Funding Sources

Bond Funded Water Capital:
​$3,450,000.00

Parking

“No-Parking” signs will be posted in advance to restrict parking in construction zones.  Please adhere to the dates and hours on the posted signs.
​

Traffic Consideration

During construction, there will be traffic lane closures; therefore, traffic disruptions shall be expected.