Underground District 62
Miraloma from 57 Fwy to Milller
Summer 2015 - Fall 2018
The work to be undertaken consists of undergrounding electrical 69kV and 12kV distributions systems street light installation, service conversions, and demolition of existing overhead facilities, in accordance with plans, specifications and contract documents.This project will replace existing 69kV and 12kV electrical systems to provide better service to Anaheim residents and businesses.
Project LocationTo see project details click the enlarge icon " [ ] " on the map below:
|
Project Features
Project TeamProject Manager: Vinh Tran
Contractor: Asplundh (714) 610-5264 City Inspector: Dany Mazraani (714) 231-8373 Funding SourcesElectric Utility fund:
$18,888,000 |
Parking“No-Parking” signs will be posted in advance to restrict parking in construction zones. Please adhere to the dates and hours on the posted signs.
|
Traffic ConsiderationDuring construction, there will be traffic lane closures; therefore, traffic disruptions shall be expected.
|
For More Information
To request this in an alternative format please call (714)765-5281 or TTY (714)765-5125. The City prohibits discrimination.

construction_notice.pdf |