Underground District No. 64
​Orangewood Avenue from Eugene Street to Lewis Street

May 2017 - Februrary 2019
This project consists of undergrounding 12kV distribution systems, street light installation, and service conversions. The project also includes reconstruction of street improvements: asphalt, sidewalk, access ramps, curb and gutter, traffic signal loops, striping, signage, and utility adjustments. This project is part of the City of Anaheim Underground Conversion Five-Year Plan.

Project Location

​To see project details click the enlarge icon " [ ] " on the map below:

Project Features

-Over 1.2 miles of new underground electrical lines and street improvements.
- Construction of related electrical substructures such as encased ductbank, conduits, and manholes.




Project Team

Project Manager: Tim Bass
Contractor: Hardy & Harper
(925)-354-7851
City Inspector: Fernando Huizar 
(714) 231-8371

Funding Sources

      Electric Utility
 Bond Funded
Electric Capital
Gas Tax
Bond Funded Water Capital
$10,207,867.36


Parking

“No-Parking” signs will be posted in advance to restrict parking in construction zones.  Please adhere to the dates and hours on the posted signs.
​

Traffic Consideration

During construction, there will be traffic lane closures; therefore, traffic disruptions shall be expected.

For More Information


To request this in an alternative format please call (714)765-5281 or TTY (714)765-5125. The City prohibits discrimination.


const._notice.2.pdf
File Size: 149 kb
File Type: pdf
Download File


Powered by Create your own unique website with customizable templates.