Calle Principia and Avenida la Vida 8" Water Main Replacement
E. Calle Principia and Avenida la Vida east of Pathfinder Trail
Summer 2018 - Fall 2018
This project consists of replacing existing ductile iron pipe with new PVC pipe
Project LocationTo see project details click the enlarge icon " [ ] " on the map below:
|
Project Features
Project TeamProject Manager: Kim Tran
Contractor: Williams Pipeline, Inc. (805) 386-2393 City Inspector: Al Finau (714) 231-6204 Funding SourcesLocal Funds: $513,000
|
Parking“No-Parking” signs will be posted in advance to restrict parking in construction zones. Please adhere to the dates and hours on the posted signs.
|
Traffic ConsiderationDuring construction, there will be traffic lane closures; therefore, traffic disruptions shall be expected.
|
For More Information
To request this in an alternative format please call (714)765-5281 or TTY (714)765-5125. The City prohibits discrimination.
Click here to upload file |