Linda Vista Complex Pump Station Improvements Phase 2

Fall 2019 - Summer 2021
The work consists of replacement of existing pumps with new up-sized pumps and motors, replacing existing electrical systems and controls, construction of a new building to house the new electrical and controls, demolition and removal of the abandoned on-site facilities, and other related site improvements.

Project Location

​To see project details click the enlarge icon " [ ] " on the map below:

Project Features

- New pumps and motors
- New electrical building
- Removal on site facilities

Project Team

Project Manager: Joel Jordan
Contractor: CALIAGUA, Inc.
Public Works Construction Services:
(714) 765-5079

Funding Sources

Water Utility Funds
$ 10,525,000.00

Parking

“No-Parking” signs will be posted in advance to restrict parking in construction zones.  Please adhere to the dates and hours on the posted signs.
​

Traffic Consideration

During construction, there will be traffic lane closures; therefore, traffic disruptions shall be expected.