La Palma Avenue and Richfield Road Storm Drain Project
The work consists of construction of a new storm drain system, riprap structures at the outlets, vault structure, removal of conflicting portions of existing RCP pipe, drywell system with a primary settling chamber, removal and replacement of landscaping, replacement of curb and gutter, and installation of asphalt pavement.
Project Information
See below for project location, latest schedule updates, and other project details:
Project FeaturesNew storm drain system
New dry well system |
Funding SourcesProp1 and Wastewater Funds
$2,400,000 |
Parking“No-Parking” signs will be posted in advance to restrict parking in construction zones. Please adhere to the dates and hours on the posted signs.
|
Traffic ConsiderationDuring construction, there will be traffic lane closures; therefore, traffic disruptions shall be expected.
|