Direct Buried Cable Replacement Phase 12

Vermont Ave., Nordica St., Stone Cir., Nylon Ave., Granite Cir., Wagner Ave., Clay St., 5601 E. Orangethorpe Ave., Imperial Hwy. and Big Sky Lane, 200 N. Wilshire Ave., and 2880 and 2901 W. Ball Rd
July 2017 - February 2018
The work consists of the replacement of direct buried electrical cables, installation of new conduits and underground structures, cables and transformers in the following locations: Vermont Ave., Nordica St., Stone Cir., Nylon Ave., Granite Cir., Wagner Ave., Clay St., 5601 E. Orangethorpe Ave., Imperial Hwy. and Big Sky Lane, 200 N. Wilshire Ave., and 2880 and 2901 W. Ball Rd.  The project will replace existing direct buried cable that is nearing the end of its life expectancy and provide better service to City of Anaheim residents and business owners. 


Project Location

​To see project details click the enlarge icon " [ ] " on the map below:

Project Features

  • Replace existing direct buried cable near the end of life expectancy
  • Provide better service to City Of Anaheim
  • New conduits and underground structures 
  • ​New cables and transformers

Project Team

Project Manager: Ted Mai
(714) 765-4123

Contractor: Asplundh
(714) 610-5264
City Inspector: Al Finau
​


Funding Sources

Electric Bond Fund Capital:
$2,967,000


Parking

“No-Parking” signs will be posted in advance to restrict parking in construction zones.  Please adhere to the dates and hours on the posted signs.
​

Traffic Consideration

During construction, there will be traffic lane closures; therefore, traffic disruptions shall be expected.

For More Information


To request this in an alternative format please call (714)765-5281 or TTY (714)765-5125. The City prohibits discrimination.


construction_notice.pdf
File Size: 56 kb
File Type: pdf
Download File


Powered by Create your own unique website with customizable templates.