Cerritos Avenue Sewer Improvements
From Euclid Street to Alley East of 9th Street
June 2017 - October 2017
This project consists of sewer improvements on Cerritos Avenue. The work to be done will consist of excavation and removal of existing 18" sewer line, construction of new 24", 12", 8", and 6" vitrified clay pipe (VCP) sewer line on Cerritos Avenue, and connecting to existing sewer laterals. This project is part of the Combined Sanitary Sewer Improvement Project to relieve the City's existing sanitary sewer needs.
Project LocationTo see project details click the enlarge icon " [ ] " on the map below:
|
Project Features~Over half a mile of new vitrified clay pipe (VCP) sewer line.
Project TeamContractor: Vasilj, Inc.
(626) 480-1442 City Inspector: Tim Flint (949) 254-7954 Funding SourcesSewer Bond: $2,127,618.33
Gas Tax: $102,666.67 |
Parking“No-Parking” signs will be posted in advance to restrict parking in construction zones. Please adhere to the dates and hours on the posted signs.
|
Traffic ConsiderationDuring construction, there will be traffic lane closures; therefore, traffic disruptions shall be expected.
|
For More Information
To request this in an alternative format please call (714)765-5281 or TTY (714)765-5125. The City prohibits discrimination.