Anaheim Hills Water Main
Anaheim Hills Road from E. Silverspur Trail to Nohl Ranch Road
Summer 2017 - Fall 2018
The work to be undertaken consists of replacing approximately 2,500 feet of existing ductile iron 8-inch pipe with a new 8-inch PVC pipe. This existing pipeline has experienced past breaks and has been determined vulnerable to further corrosion damage and considered at risk for future failures.
Project LocationTo see project details click the enlarge icon " [ ] " on the map below:
|
Project Features
Project TeamProject Manager: Lisa O'Connell
Contractor: Vido Samarzich, Inc (909) 987-6377 City Inspector: Brian Moore (714) 765- 4648 Funding SourcesBonded Funded Water Capital:
$900,000 |
Parking“No-Parking” signs will be posted in advance to restrict parking in construction zones. Please adhere to the dates and hours on the posted signs.
|
Traffic ConsiderationDuring construction, there will be traffic lane closures; therefore, traffic disruptions shall be expected.
|
For More Information
To request this in an alternative format please call (714)765-5281 or TTY (714)765-5125. The City prohibits discrimination.
construction_notice.pdf |