Alley Sewer Improvements
East of Claudina, Emily, and Philadelphia from Water to South Street
January 2017 - March 2017
This project consists of sewer improvements in the alleys east of Claudina Street, Emily Street, and Philadelphia Street from South Street to Water Street. The work to be done will consist of excavation and removal of existing sanitary sewer facilities, and installation of new 8" vitrified clay sewer pipe (VCP). New concrete alley ways will also be constructed.
Project LocationTo see project details click the enlarge icon " [ ] " on the map below:
|
Project Features~2400 feet of new 8" VCP sewer pipe and new concrete alley ways.
Project TeamContractor: Miramontes Construction Company, Inc.
(909) 787-3012 City Inspector: Tim Flint (949) 254-7954 Funding SourcesWastewater Fund
$1,299,905.00 |
Parking“No-Parking” signs will be posted in advance to restrict parking in construction zones. Please adhere to the dates and hours on the posted signs.
|
Traffic ConsiderationDuring construction, there will be traffic lane closures; therefore, traffic disruptions shall be expected.
|